New Toll Free Phone Number   866-921-2628
counter
270-866-2628 
Paul@woodiesrestorations.com
1983 Midnight Lace 
7/31/14 
The swimming platform has been bleached.  
<< Page One
8/01/14 
The mast has received a coat of sealer. 
8/04/14 
The swim platform has received one coat of varnish. 

The mast has received the final coats of paint and clear coat. 

8/07/14 
The swimming platform has received a second coat of varnish. 

9/03/14 
The transom has been sanded. 

9/11/14 
​Fairing compound has been applied to the bottom.
9/30/14 
Four coats of epoxy has been applied, along with fairing compound. 
Four coats of epoxy has been applied, along with fairing compound. 
10/2/14 
The bottom is being sanded. 
10/8/14 
The portside has been completely sanded. 
10/24/14 
The hallway has been sanded. 
11/04/14 
The last of the bottom paint is being stripped off. 
11/11/14 
The first coat of bottom paint has been painted. 
11/12/14 
The props were delivered today. 
11/19/14 
Progress on the inside.
11/24/14 
The bottom received two coats of white paint. 
11/24/14 
The Midnight Lace is being lifted to take weight off the keel block in order to make sure the entire bottom will be painted.
12/04/14 
Progress made on the front of the cabin. 
12/11/14

The swimming platform. 
We installed a bung on the left side and would like to install one on the adjacent side. 
12/05/14
The plumbing has been installed under the guest sink.
12/12/14
The bung was installed on the right side of the swimming platform. 
2/12/15
The swim platform has received another coat of varnish. 
3/4/15
A coat of varnish has been applied to the transom. 
3/14/15
The vacu-flush has been plumbed in.
3/16/15
Made lids and put on the top pf water tanks. The old hardware was replaced on the old lids and fastened down. 
3/17/15
The area where the mast will be place, has been painted. 
The through holes are in place. 
The vacu-flush is hooked up. 
3/18/15
The swim platform.
3/25/15
The salon thru hole has been installed. 
3/26/15
More thru holes have been installed. 
3/27/15
Installing the mast. 
The mast installed. 
4/3/15
The fiberglass is cracking on the inside ceiling from the mast. 
The tank tenders have been installed.
4/10/15
Installed the through hulls valves.
Fabricated the handle on the manual bilge pump because original handle was touching the floor on the down stroke. 
The engine strainers are installed. 
Transducer is installed. 
4/14/15
The bracket for the mast is in the process of being installed. 
The wooden brackets have been replaced with metal ones.  
4/16/15
The bilge pump hoses are being installed. 
4/22/15
The bilge pump hoses are being installed. 
The macerator pump has been installed, along with the new line. 
4/30/15
The starboard side has received a white coat and now has the grey barrier coat. 
5/04/15
The bilge pumps switches and brackets have been installed in the salon, in front of the fuel tanks and lazerette. The hose has been ran and the strainers for the bilge pump in the forward salon. 
5/05/15
The strainers are installed. 
The new varnish on the swim platform. 
Page Three>>