1968 Chris Craft 33'
            Futura 
<< Page 1
6/16/14
The screws holes on the cockpit roof are being filled. 
6/18/14
The life savor rings are in with the name on them. 
The vinyl has been installed on the cockpit roof. 
6/19/14
The trim has been installed.
6/20/14
The A.C box has been created and stained. 
This is where we want to paint the stripes. 
6/23/14
Rot on the deck near the left window. 
The A.C. box has bee installed. 
The inside view of the patch. 
The outside view of the patch on the deck. 
6/24/14
The window frame has been sanded for paint. 
6/25/14
The trim was installed under the window. 
The vinyl has been put back over the patches. 
Rot was found in between the windows and patched. 
6/26/14
The portside window has received the first coat of paint. 
The portside window has received the first coat of paint. 
Small holes have been filled on the starboard side window frame, and the window trim on all sides has been sanded and prepped for paint. 
The rot that was found on the bottom starboard side is being repaired. 
6/27/14
The registration plates have arrived. 
The rot on the bottom starboard side has been patched. 
Another rotted spot was found on the bottom port side. 
6/30/14
The anchor mount has been put on the front of the boat. 
7/1/14
The registration plates are ready to be put on the boat upon delivery.  
The headliner has been installed in the bathroom. 
The spotlight and the radar mount have been installed on the cockpit roof. 
The sink cover has been varnished. 
The window trim and the broken strut barring. 
7/2/14
The vinyl is being put on the deck panels. 
7/2/14
The vinyl has been installed on all deck panels.
7/8/14
The trim has been installed on the refrigerator door, along with spacers behind the hinges so the door will completely close. The inside refrigerator had a block place behind the handle for complete closure. 
The rot is being repaired on the port side bottom. 
The buttblocks are in place and the patch is being put on. 
7/9/14
The patch has been installed. 
7/15/14
Areas on the bottom have been sanded and it is being prepped for paint. 

7/18/14
Bottom of boat
Inside of Boat
Poured epoxy in shaft log hole to fill a pre-existing void in the plywood. Installed screws in bottom to insure a good seal. 
The new hinges have been installed on the hatchs. 
Polished and re-installed fridge support and hardware. 
The strut barrings have been installed on each side. 
The hand rails were installed on both sides. 
The inside window trim is being painted. 
7/22/14
Rot was repaired on the starboard side of the cockpit coaming. 
The trim (inside and out) is receiving a second coat.
The shaft logs are being cleaned and prefitted. 
Inside of boat.
7/23/14
The metal has been installed under the door. 
7/24/14
The binding is being installed on the carpet. 
The shaft hubs are being cleaned and the key is being made.
The shaft hubs are also being painted. 
7/25/14
The sides are being prepped for the final paint. 
The flagpole has been stained.
7/28/14
The sides have been painted and the transom has also received varnish. 
7/29/14
The bottom is being painted.
The  new breaker box has been installed. The old one had miss wiring. 
The shore power plug has been installed.
The switch as been installed.
7/30/14
The window trim is being installed.
The rub rail has been installed on the swim platform. 
7/31/14
The window screen has been installed. 
8/01/14
The mast has been installed.
The switch for the spot light has been installed. 
 Page 3 >>